RUB » Physics » The Faculty » Chairs and Working Groups » EP1 » PANDA FEMC Production Database

Show Hamamatsu Avalanche Photo Diode 1307014071 - Archived data from Wed, 07. October 2020 15:46:05 CEST


This is all the information about APD 1307014071. If it is wrong, edit the data.

Subdetector specification:  
Serial: 1307014071
Type: Hamamatsu Avalanche Photo Diode
Detector: unassigned
Unit: unassigned
Preamp: 0
Current location: In transit to Mainz
   
Installation information:  
Label: none
   
Manufacturer information:  
Wafer position: E09
Break-through voltage: 436.4 V
Voltage for Gain 100 (T=+25°C): 407.8 V
Dark current: 5.37 nA
   
Screening Logistics:  
Available: Yes
Storage Box: 45
Position in Box: 20
EP1 batch: none
EP1 batch after irradiation: none
   
Shipment:  
Grid number: 312
Position in grid: 5
Arrival for irradiation: 02. Nov 2016
Sent for analysis after irradiation: 10. Nov 2016
Return for assembly: 09. Dec 2016
   
Irradiation:  
Date: 04. Nov 2016
Dose used: 30 Gy
Temperature: 20 °C
Position: 1
Bias voltage: 350 V     (connected)
   
Annealing:  
Date: none
Temperature: none
Duration: none
   
Measurement results:  
Voltage for Gain 100: T = +20 °C: 408.4881122 V     T = -25 °C: 371.6529668 V
Voltage for Gain 150: T = +20 °C: 416.5811923 V     T = -25 °C: 379.4984923 V
Voltage for Gain 200: T = +20 °C: 420.9682438 V     T = -25 °C: 383.9213592 V
Gain/Voltage slope at M = 100: T = +20 °C: 4.53929355 V-1     T = -25 °C: 4.599873707 V-1
Gain/Voltage slope at M = 150: T = +20 °C: 10.24850207 V-1     T = -25 °C: 9.564365826 V-1
Gain/Voltage slope at M = 200: T = +20 °C: 12.8283022 V-1     T = -25 °C: 13.53265688 V-1
Break-through voltage: T = +20 °C: 436.6520592 V     T = -25 °C: 399.5475334 V
   
Notes:


Version history

Time Author Change comment
05. Feb 2021 10:53:58 CET jreher Updated box and position via API.
03. Feb 2021 18:19:46 CET jreher Updated box and position via API.
07. Oct 2020 15:46:05 CEST jreher Updated APD location via API.
11. Aug 2020 17:27:02 CEST jreher Updated APD characteristics via API.
27. Nov 2019 19:36:59 CET jreher Updated APD location via API.
25. Nov 2019 17:14:29 CET jreher Updated box and position via API.
04. Jul 2019 11:11:44 CEST jreher Updated APD location via API.
13. Jun 2019 10:01:33 CEST jreher Updated APD batch assignment via API.
09. Dec 2016 10:27:42 CET markus.moritz Entered return for assembly date.
23. Nov 2016 10:53:04 CET markus.moritz Entered shipped after irradiation date.
04. Nov 2016 16:01:16 CET markus.moritz Entered irradiation information.
02. Nov 2016 14:51:07 CET markus.moritz Entered arrival for irradiation date.
01. Aug 2016 17:28:32 CEST Tobias Assigned to grid via information extracted from APD DB.
22. Jun 2016 15:41:05 CEST Tobias Imported from Hamamatsu datasheet.