RUB » Physics » The Faculty » Chairs and Working Groups » EP1 » PANDA FEMC Production Database

Show Hamamatsu Avalanche Photo Diode 0801007273 - Archived data from Wed, 03. February 2021 18:20:54 CET


This is all the information about APD 0801007273. If it is wrong, edit the data.

Subdetector specification:  
Serial: 0801007273
Type: Hamamatsu Avalanche Photo Diode
Detector: unassigned
Unit: unassigned
Preamp: 0
Current location: Bochum
   
Installation information:  
Label: none
   
Manufacturer information:  
Wafer position: D14
Break-through voltage: 416 V
Voltage for Gain 100 (T=+25°C): 387 V
Dark current: 3.7 nA
   
Screening Logistics:  
Available: Yes
Storage Box: 54
Position in Box: 34
EP1 batch: none
EP1 batch after irradiation: none
   
Shipment:  
Grid number: none
Position in grid: none
Arrival for irradiation: 18. Apr 2019
Sent for analysis after irradiation: 04. Jun 2019
Return for assembly: none
   
Irradiation:  
Date: 29. May 2019
Dose used: 37 Gy
Temperature: 20 °C
Position: none
Bias voltage: none     
   
Annealing:  
Date: 29. May 2019
Temperature: 80 °C
Duration: 48 h
   
Measurement results:  
Voltage for Gain 100: T = +20 °C: 387.3127904 V     T = -25 °C: 350.8534041 V
Voltage for Gain 150: T = +20 °C: 395.2386917 V     T = -25 °C: 358.4127986 V
Voltage for Gain 200: T = +20 °C: 399.6102293 V     T = -25 °C: 362.652351 V
Gain/Voltage slope at M = 100: T = +20 °C: 4.408892178 V-1     T = -25 °C: 4.823292453 V-1
Gain/Voltage slope at M = 150: T = +20 °C: 8.486577268 V-1     T = -25 °C: 8.7744755 V-1
Gain/Voltage slope at M = 200: T = +20 °C: 14.99294641 V-1     T = -25 °C: 15.29880824 V-1
Break-through voltage: T = +20 °C: 415.4575853 V     T = -25 °C: 378.6438665 V
   
Notes:


Version history

Time Author Change comment
05. Feb 2021 10:55:20 CET jreher Updated box and position via API.
03. Feb 2021 18:20:54 CET jreher Updated box and position via API.
11. Aug 2020 17:27:51 CEST jreher Updated APD characteristics via API.
27. Nov 2019 19:38:16 CET jreher Updated APD location via API.
25. Nov 2019 17:15:11 CET jreher Updated box and position via API.
04. Jul 2019 11:12:36 CEST jreher Updated APD location via API.
18. Jun 2019 13:42:20 CEST jgrochowski Updated APD batch assignment via API.
04. Jun 2019 15:02:32 CEST markus.moritz
22. Jun 2016 15:22:33 CEST Tobias Imported from Hamamatsu datasheet.