Serial: 1203012903
Type: Hamamatsu Avalanche Photo Diode
Detector: unassigned
Unit: unassigned
Preamp: 0
Current location: In transit to Mainz
   
Installation information:  
Label: none
   
Manufacturer information:  
Wafer position: D11
Break-through voltage: 443 V
Voltage for Gain 100 (T=+25°C): 414.2 V
Dark current: 10.8 nA
   
Screening Logistics:  
Available: Yes
Storage Box: 304
Position in Box: 12
EP1 batch: none
EP1 batch after irradiation: none
   
Shipment:  
Grid number: 259
Position in grid: 6
Arrival for irradiation: 29. Sep 2017
Sent for analysis after irradiation: 20. Oct 2017
Return for assembly: none
   
Irradiation:  
Date: 16. Oct 2017
Dose used: 45 Gy
Temperature: 20 °C
Position: 2
Bias voltage: 414.2 V     (connected)
   
Annealing:  
Date: none
Temperature: none
Duration: none
   
Measurement results:  
Voltage for Gain 100: T = +20 °C: 415.0314144 V     T = -25 °C: 379.0248012 V
Voltage for Gain 150: T = +20 °C: 423.0052301 V     T = -25 °C: 387.1478012 V
Voltage for Gain 200: T = +20 °C: 427.4430789 V     T = -25 °C: 390.5837336 V
Gain/Voltage slope at M = 100: T = +20 °C: 4.533094369 V-1     T = -25 °C: 4.653102627 V-1
Gain/Voltage slope at M = 150: T = +20 °C: 8.842999599 V-1     T = -25 °C: 10.11865392 V-1
Gain/Voltage slope at M = 200: T = +20 °C: 13.65329256 V-1     T = -25 °C: 15.49404386 V-1
Break-through voltage: T = +20 °C: 439.9688281 V     T = -25 °C: 405.9159029 V
   
Notes:


Version history

Time Author Change comment
05. Feb 2021 11:27:31 CET jreher Updated box and position via API.
07. Oct 2020 15:45:06 CEST jreher Updated APD location via API.
11. Aug 2020 17:57:49 CEST jreher Updated APD characteristics via API.
21. Jul 2020 14:43:54 CEST jreher Updated APD location via API.
21. Jul 2020 14:43:45 CEST jreher Updated box and position via API.
19. Dec 2019 16:19:59 CET spankonin Updated APD batch assignment via API.
19. Dec 2019 15:18:20 CET jreher Updated box and position via API.
20. Oct 2017 14:31:16 CEST markus.moritz Entered shipped after irradiation date.
20. Oct 2017 09:54:14 CEST markus.moritz Entered irradiation information.
29. Sep 2017 11:51:47 CEST markus.moritz Entered arrival for irradiation date.
01. Aug 2016 17:27:56 CEST Tobias Assigned to grid via information extracted from APD DB.
22. Jun 2016 15:37:52 CEST Tobias Imported from Hamamatsu datasheet.