RUB » Physics » The Faculty » Chairs and Working Groups » EP1 » PANDA FEMC Production Database

Show Hamamatsu Avalanche Photo Diode 0822008926 - Archived data from Fri, 05. February 2021 11:13:48 CET


This is all the information about APD 0822008926. If it is wrong, edit the data.

Subdetector specification:  
Serial: 0822008926
Type: Hamamatsu Avalanche Photo Diode
Detector: unassigned
Unit: unassigned
Preamp: 0
Current location: Bochum
   
Installation information:  
Label: none
   
Manufacturer information:  
Wafer position: C09
Break-through voltage: 411 V
Voltage for Gain 100 (T=+25°C): 382.3 V
Dark current: 5.8 nA
   
Screening Logistics:  
Available: Yes
Storage Box: 197
Position in Box: 24
EP1 batch: none
EP1 batch after irradiation: none
   
Shipment:  
Grid number: none
Position in grid: none
Arrival for irradiation: 18. Apr 2019
Sent for analysis after irradiation: 29. Jul 2019
Return for assembly: none
   
Irradiation:  
Date: 25. Jul 2019
Dose used: 37 Gy
Temperature: 20 °C
Position: none
Bias voltage: none     
   
Annealing:  
Date: 27. Jul 2019
Temperature: 80 °C
Duration: 48 h
   
Measurement results:  
Voltage for Gain 100: T = +20 °C: 382.9190369 V     T = -25 °C: 347.4387731 V
Voltage for Gain 150: T = +20 °C: 390.7879946 V     T = -25 °C: 354.812118 V
Voltage for Gain 200: T = +20 °C: 395.1398099 V     T = -25 °C: 358.9440804 V
Gain/Voltage slope at M = 100: T = +20 °C: 4.623107912 V-1     T = -25 °C: 4.757184367 V-1
Gain/Voltage slope at M = 150: T = +20 °C: 9.162664888 V-1     T = -25 °C: 9.646800529 V-1
Gain/Voltage slope at M = 200: T = +20 °C: 14.28830733 V-1     T = -25 °C: 15.2838132 V-1
Break-through voltage: T = +20 °C: 409.8931658 V     T = -25 °C: 373.75724 V
   
Notes:


Version history

Time Author Change comment
20. Oct 2021 09:35:54 CEST oafedulidis Assigned to capsule by script
21. Apr 2021 11:01:30 CEST jreher Updated box and position via API.
05. Feb 2021 11:13:48 CET jreher Updated box and position via API.
11. Aug 2020 17:36:50 CEST jreher Updated APD characteristics via API.
27. Nov 2019 20:03:57 CET jreher Updated APD location via API.
25. Nov 2019 17:26:24 CET jreher Updated box and position via API.
13. Aug 2019 14:51:44 CEST spankonin Updated APD batch assignment via API.
08. Aug 2019 14:39:26 CEST markus.moritz
22. Jun 2016 15:29:43 CEST Tobias Imported from Hamamatsu datasheet.