RUB » Physics » The Faculty » Chairs and Working Groups » EP1 » PANDA FEMC Production Database

Show Hamamatsu Avalanche Photo Diode 2910033137 - Archived data from Tue, 16. February 2021 12:27:19 CET


This is all the information about APD 2910033137. If it is wrong, edit the data.

Subdetector specification:  
Serial: 2910033137
Type: Hamamatsu Avalanche Photo Diode
Detector: unassigned
Unit: unassigned
Preamp: 0
Current location: Bochum
   
Installation information:  
Label: none
   
Manufacturer information:  
Wafer position: C06
Break-through voltage: 409 V
Voltage for Gain 100 (T=+25°C): 380.3 V
Dark current: 6.5 nA
   
Screening Logistics:  
Available: Yes
Storage Box: 110
Position in Box: 24
EP1 batch: 113
EP1 batch after irradiation: none
   
Shipment:  
Grid number: none
Position in grid: none
Arrival for irradiation: none
Sent for analysis after irradiation: none
Return for assembly: none
   
Irradiation:  
Date: none
Dose used: none
Temperature: none
Position: none
Bias voltage: none     
   
Annealing:  
Date: none
Temperature: none
Duration: none
   
Measurement results:  
Voltage for Gain 100: T = +20 °C: 380.7990682 V     T = -25 °C: 345.3944921 V
Voltage for Gain 150: T = +20 °C: 388.6173317 V     T = -25 °C: 352.7598412 V
Voltage for Gain 200: T = +20 °C: 392.959033 V     T = -25 °C: 356.8762036 V
Gain/Voltage slope at M = 100: T = +20 °C: 4.701765591 V-1     T = -25 °C: 4.804769113 V-1
Gain/Voltage slope at M = 150: T = +20 °C: 9.365033932 V-1     T = -25 °C: 9.804625768 V-1
Gain/Voltage slope at M = 200: T = +20 °C: 14.68036358 V-1     T = -25 °C: 15.57357153 V-1
Break-through voltage: T = +20 °C: 408.4375657 V     T = -25 °C: 372.0890409 V
   
Notes:


Version history

Time Author Change comment
17. Jun 2021 19:22:24 CEST oafedulidis Assigned to capsule by script
16. Feb 2021 12:27:19 CET jreher Updated box and position via API.
05. Feb 2021 11:02:33 CET jreher Updated box and position via API.
11. Aug 2020 18:00:27 CEST jreher Updated APD characteristics via API.
11. Aug 2020 17:49:14 CEST jreher Updated APD location via API.
28. Jan 2020 16:03:05 CET spankonin Updated APD batch assignment via API.
29. Nov 2019 11:46:46 CET jreher Updated APD location via API.
28. Nov 2019 12:12:53 CET jreher Updated box and position via API.
27. Nov 2019 19:48:04 CET jreher Updated APD location via API.
23. Aug 2019 12:01:51 CEST jgrochowski Updated APD batch assignment via API.
03. Jan 2019 00:14:14 CET Tobias Corrected dark current unit.
06. Jul 2018 22:38:43 CEST Tobias Imported from Hamamatsu datasheet.