Serial: 2812031722
Type: Hamamatsu Avalanche Photo Diode
Detector: unassigned
Unit: unassigned
Preamp: 0
Current location: Bochum
   
Installation information:  
Label: none
   
Manufacturer information:  
Wafer position: C13
Break-through voltage: 414 V
Voltage for Gain 100 (T=+25°C): 386.2 V
Dark current: 7.6 nA
   
Screening Logistics:  
Available: Yes
Storage Box: 92
Position in Box: 10
EP1 batch: 83
EP1 batch after irradiation: none
   
Shipment:  
Grid number: none
Position in grid: none
Arrival for irradiation: none
Sent for analysis after irradiation: none
Return for assembly: none
   
Irradiation:  
Date: none
Dose used: none
Temperature: none
Position: none
Bias voltage: none     
   
Annealing:  
Date: none
Temperature: none
Duration: none
   
Measurement results:  
Voltage for Gain 100: T = +20 °C: 386.8445279 V     T = -25 °C: 351.4911764 V
Voltage for Gain 150: T = +20 °C: 394.6952096 V     T = -25 °C: 358.9549055 V
Voltage for Gain 200: T = +20 °C: 399.0370452 V     T = -25 °C: 363.125819 V
Gain/Voltage slope at M = 100: T = +20 °C: 4.653933665 V-1     T = -25 °C: 4.664226883 V-1
Gain/Voltage slope at M = 150: T = +20 °C: 9.290619627 V-1     T = -25 °C: 9.384009372 V-1
Gain/Voltage slope at M = 200: T = +20 °C: 14.5776632 V-1     T = -25 °C: 12.24398493 V-1
Break-through voltage: T = +20 °C: 413.9028826 V     T = -25 °C: 377.0768239 V
   
Notes:


Version history

Time Author Change comment
05. Feb 2021 11:00:10 CET jreher Updated box and position via API.
03. Feb 2021 18:25:39 CET jreher Updated box and position via API.
11. Aug 2020 18:04:48 CEST jreher Updated APD characteristics via API.
11. Aug 2020 17:55:06 CEST jreher Updated APD location via API.
17. Feb 2020 17:54:22 CET spankonin Updated APD batch assignment via API.
29. Nov 2019 11:50:33 CET jreher Updated APD location via API.
27. Nov 2019 19:45:10 CET jreher Updated APD location via API.
25. Nov 2019 17:18:13 CET jreher Updated box and position via API.
20. Aug 2019 12:33:55 CEST jgrochowski Updated APD batch assignment via API.
05. Jul 2019 13:48:28 CEST jreher Updated APD location via API.
03. Jan 2019 00:13:45 CET Tobias Corrected dark current unit.
20. Jun 2018 13:36:07 CEST Tobias Imported from Hamamatsu datasheet.