RUB » Physics » The Faculty » Chairs and Working Groups » EP1 » PANDA FEMC Production Database

Show Hamamatsu Avalanche Photo Diode 2811031638 - Archived data from Wed, 03. February 2021 18:25:30 CET


This is all the information about APD 2811031638. If it is wrong, edit the data.

Subdetector specification:  
Serial: 2811031638
Type: Hamamatsu Avalanche Photo Diode
Detector: unassigned
Unit: unassigned
Preamp: 0
Current location: Bochum
   
Installation information:  
Label: none
   
Manufacturer information:  
Wafer position: B05
Break-through voltage: 413 V
Voltage for Gain 100 (T=+25°C): 384.9 V
Dark current: 5.1 nA
   
Screening Logistics:  
Available: Yes
Storage Box: 91
Position in Box: 3
EP1 batch: 82
EP1 batch after irradiation: none
   
Shipment:  
Grid number: none
Position in grid: none
Arrival for irradiation: none
Sent for analysis after irradiation: none
Return for assembly: none
   
Irradiation:  
Date: none
Dose used: none
Temperature: none
Position: none
Bias voltage: none     
   
Annealing:  
Date: none
Temperature: none
Duration: none
   
Measurement results:  
Voltage for Gain 100: T = +20 °C: 385.0702536 V     T = -25 °C: 349.2696727 V
Voltage for Gain 150: T = +20 °C: 392.8944135 V     T = -25 °C: 356.7856781 V
Voltage for Gain 200: T = +20 °C: 397.2393399 V     T = -25 °C: 360.9684835 V
Gain/Voltage slope at M = 100: T = +20 °C: 4.479853102 V-1     T = -25 °C: 4.772796499 V-1
Gain/Voltage slope at M = 150: T = +20 °C: 9.006151351 V-1     T = -25 °C: 9.766200546 V-1
Gain/Voltage slope at M = 200: T = +20 °C: 14.25477584 V-1     T = -25 °C: 15.17457237 V-1
Break-through voltage: T = +20 °C: 412.851592 V     T = -25 °C: 376.6295089 V
   
Notes:


Version history

Time Author Change comment
03. May 2021 10:27:27 CEST oafedulidis Updated box and position via API.
05. Feb 2021 11:00:02 CET jreher Updated box and position via API.
03. Feb 2021 18:25:30 CET jreher Updated box and position via API.
11. Aug 2020 18:04:36 CEST jreher Updated APD characteristics via API.
11. Aug 2020 17:55:00 CEST jreher Updated APD location via API.
17. Feb 2020 17:55:23 CET spankonin Updated APD batch assignment via API.
29. Nov 2019 11:50:29 CET jreher Updated APD location via API.
27. Nov 2019 19:44:58 CET jreher Updated APD location via API.
25. Nov 2019 17:18:08 CET jreher Updated box and position via API.
20. Aug 2019 12:32:45 CEST jgrochowski Updated APD batch assignment via API.
05. Jul 2019 13:48:20 CEST jreher Updated APD location via API.
03. Jan 2019 00:13:43 CET Tobias Corrected dark current unit.
20. Jun 2018 13:36:05 CEST Tobias Imported from Hamamatsu datasheet.