RUB » Physics » The Faculty » Chairs and Working Groups » EP1 » PANDA FEMC Production Database

Show Hamamatsu Avalanche Photo Diode 2803031028 - Archived data from Fri, 05. February 2021 10:59:18 CET


This is all the information about APD 2803031028. If it is wrong, edit the data.

Subdetector specification:  
Serial: 2803031028
Type: Hamamatsu Avalanche Photo Diode
Detector: unassigned
Unit: unassigned
Preamp: 0
Current location: Bochum
   
Installation information:  
Label: none
   
Manufacturer information:  
Wafer position: E14
Break-through voltage: 407 V
Voltage for Gain 100 (T=+25°C): 378.7 V
Dark current: 15.2 nA
   
Screening Logistics:  
Available: Yes
Storage Box: 85
Position in Box: 21
EP1 batch: 73
EP1 batch after irradiation: none
   
Shipment:  
Grid number: none
Position in grid: none
Arrival for irradiation: 26. Aug 2019
Sent for analysis after irradiation: 02. Sep 2019
Return for assembly: none
   
Irradiation:  
Date: 28. Aug 2019
Dose used: 37 Gy
Temperature: 20 °C
Position: none
Bias voltage: none     
   
Annealing:  
Date: 31. Aug 2019
Temperature: 80 °C
Duration: 48 h
   
Measurement results:  
Voltage for Gain 100: T = +20 °C: 378.9108672 V     T = -25 °C: 343.6203653 V
Voltage for Gain 150: T = +20 °C: 386.7497604 V     T = -25 °C: 350.990487 V
Voltage for Gain 200: T = +20 °C: 391.116792 V     T = -25 °C: 355.1300739 V
Gain/Voltage slope at M = 100: T = +20 °C: 4.684861805 V-1     T = -25 °C: 4.743679435 V-1
Gain/Voltage slope at M = 150: T = +20 °C: 9.219578974 V-1     T = -25 °C: 9.543175748 V-1
Gain/Voltage slope at M = 200: T = +20 °C: 14.37020853 V-1     T = -25 °C: 15.09640149 V-1
Break-through voltage: T = +20 °C: 406.6441539 V     T = -25 °C: 370.3796151 V
   
Notes:


Version history

Time Author Change comment
20. Oct 2021 09:32:15 CEST oafedulidis Assigned to capsule by script
15. Apr 2021 17:00:50 CEST jreher Updated box and position via API.
05. Feb 2021 10:59:18 CET jreher Updated box and position via API.
03. Feb 2021 18:24:48 CET jreher Updated box and position via API.
11. Aug 2020 17:39:03 CEST jreher Updated APD characteristics via API.
27. Nov 2019 19:43:54 CET jreher Updated APD location via API.
25. Nov 2019 17:17:39 CET jreher Updated box and position via API.
13. Sep 2019 10:28:55 CEST jgrochowski Updated APD batch assignment via API.
04. Sep 2019 13:20:02 CEST markus.moritz
25. Jul 2019 12:12:15 CEST spankonin Updated APD batch assignment via API.
05. Jul 2019 13:47:34 CEST jreher Updated APD location via API.
03. Jan 2019 00:13:34 CET Tobias Corrected dark current unit.
24. May 2018 14:39:23 CEST Tobias Updated location to "Bochum".
18. May 2018 12:05:27 CEST Tobias Imported from Hamamatsu datasheet.