RUB » Physics » The Faculty » Chairs and Working Groups » EP1 » PANDA FEMC Production Database

Show Hamamatsu Avalanche Photo Diode 2709030713 - Archived data from Fri, 05. February 2021 10:58:49 CET


This is all the information about APD 2709030713. If it is wrong, edit the data.

Subdetector specification:  
Serial: 2709030713
Type: Hamamatsu Avalanche Photo Diode
Detector: unassigned
Unit: unassigned
Preamp: 0
Current location: Bochum
   
Installation information:  
Label: none
   
Manufacturer information:  
Wafer position: A08
Break-through voltage: 419 V
Voltage for Gain 100 (T=+25°C): 390.6 V
Dark current: 6.3 nA
   
Screening Logistics:  
Available: Yes
Storage Box: 81
Position in Box: 48
EP1 batch: 67
EP1 batch after irradiation: none
   
Shipment:  
Grid number: none
Position in grid: none
Arrival for irradiation: 26. Aug 2019
Sent for analysis after irradiation: 02. Sep 2019
Return for assembly: none
   
Irradiation:  
Date: 28. Aug 2019
Dose used: 37 Gy
Temperature: 20 °C
Position: none
Bias voltage: none     
   
Annealing:  
Date: 31. Aug 2019
Temperature: 80 °C
Duration: 48 h
   
Measurement results:  
Voltage for Gain 100: T = +20 °C: 390.8791091 V     T = -25 °C: 354.8292846 V
Voltage for Gain 150: T = +20 °C: 398.7605355 V     T = -25 °C: 362.3972267 V
Voltage for Gain 200: T = +20 °C: 403.1242102 V     T = -25 °C: 366.640646 V
Gain/Voltage slope at M = 100: T = +20 °C: 4.625249643 V-1     T = -25 °C: 4.87045274 V-1
Gain/Voltage slope at M = 150: T = +20 °C: 9.206925143 V-1     T = -25 °C: 8.890002611 V-1
Gain/Voltage slope at M = 200: T = +20 °C: 14.40268858 V-1     T = -25 °C: 15.60503589 V-1
Break-through voltage: T = +20 °C: 417.8354045 V     T = -25 °C: 381.4688425 V
   
Notes:


Version history

Time Author Change comment
16. Nov 2022 09:58:58 CET oafedulidis Assigned to capsule by script
16. Dec 2021 13:42:35 CET oafedulidis Updated box and position via API.
05. Feb 2021 10:58:49 CET jreher Updated box and position via API.
03. Feb 2021 18:24:20 CET jreher Updated box and position via API.
11. Aug 2020 17:38:30 CEST jreher Updated APD characteristics via API.
27. Nov 2019 19:43:12 CET jreher Updated APD location via API.
25. Nov 2019 17:17:22 CET jreher Updated box and position via API.
10. Sep 2019 11:21:40 CEST jgrochowski Updated APD batch assignment via API.
04. Sep 2019 11:26:52 CEST markus.moritz
25. Jul 2019 12:13:46 CEST spankonin Updated APD batch assignment via API.
05. Jul 2019 13:47:04 CEST jreher Updated APD location via API.
03. Jan 2019 00:13:27 CET Tobias Corrected dark current unit.
24. May 2018 14:39:23 CEST Tobias Updated location to "Bochum".
18. May 2018 12:04:20 CEST Tobias Imported from Hamamatsu datasheet.