RUB » Physics » The Faculty » Chairs and Working Groups » EP1 » PANDA FEMC Production Database

Show Hamamatsu Avalanche Photo Diode 2515028716 - Archived data from Tue, 11. August 2020 17:32:46 CEST


This is all the information about APD 2515028716. If it is wrong, edit the data.

Subdetector specification:  
Serial: 2515028716
Type: Hamamatsu Avalanche Photo Diode
Detector: unassigned
Unit: unassigned
Preamp: 0
Current location: Bochum
   
Installation information:  
Label: none
   
Manufacturer information:  
Wafer position: B10
Break-through voltage: 415 V
Voltage for Gain 100 (T=+25°C): 387 V
Dark current: 4.5 nA
   
Screening Logistics:  
Available: Yes
Storage Box: 62
Position in Box: 24
EP1 batch: 38
EP1 batch after irradiation: none
   
Shipment:  
Grid number: none
Position in grid: none
Arrival for irradiation: 16. Jul 2019
Sent for analysis after irradiation: 19. Jul 2019
Return for assembly: none
   
Irradiation:  
Date: 16. Jul 2019
Dose used: 37 Gy
Temperature: 20 °C
Position: none
Bias voltage: none     
   
Annealing:  
Date: 17. Jul 2019
Temperature: 80 °C
Duration: 48 h
   
Measurement results:  
Voltage for Gain 100: T = +20 °C: 387.5803259 V     T = -25 °C: 351.4967721 V
Voltage for Gain 150: T = +20 °C: 395.4121882 V     T = -25 °C: 358.9768854 V
Voltage for Gain 200: T = +20 °C: 399.7436048 V     T = -25 °C: 363.1684965 V
Gain/Voltage slope at M = 100: T = +20 °C: 4.400411279 V-1     T = -25 °C: 4.684030915 V-1
Gain/Voltage slope at M = 150: T = +20 °C: 8.683968044 V-1     T = -25 °C: 9.384476244 V-1
Gain/Voltage slope at M = 200: T = +20 °C: 15.13660844 V-1     T = -25 °C: 14.79295187 V-1
Break-through voltage: T = +20 °C: 414.390599 V     T = -25 °C: 378.1313886 V
   
Notes:


Version history

Time Author Change comment
05. Feb 2021 10:56:19 CET jreher Updated box and position via API.
03. Feb 2021 18:21:53 CET jreher Updated box and position via API.
11. Aug 2020 17:32:46 CEST jreher Updated APD characteristics via API.
27. Nov 2019 19:39:43 CET jreher Updated APD location via API.
25. Nov 2019 17:15:46 CET jreher Updated box and position via API.
01. Aug 2019 12:12:01 CEST spankonin Updated APD batch assignment via API.
24. Jul 2019 14:05:51 CEST markus.moritz
05. Jul 2019 13:44:32 CEST jreher Updated APD location via API.
01. Jul 2019 14:29:45 CEST spankonin Updated APD batch assignment via API.
03. Jan 2019 00:12:29 CET Tobias Corrected dark current unit.
12. Jan 2018 13:12:11 CET Tobias Imported from Hamamatsu datasheet.