RUB » Physics » The Faculty » Chairs and Working Groups » EP1 » PANDA FEMC Production Database

Show Hamamatsu Avalanche Photo Diode 2510028259 - Archived data from Fri, 05. February 2021 11:10:24 CET


This is all the information about APD 2510028259. If it is wrong, edit the data.

Subdetector specification:  
Serial: 2510028259
Type: Hamamatsu Avalanche Photo Diode
Detector: unassigned
Unit: unassigned
Preamp: 0
Current location: Bochum
   
Installation information:  
Label: none
   
Manufacturer information:  
Wafer position: F09
Break-through voltage: 406 V
Voltage for Gain 100 (T=+25°C): 377.3 V
Dark current: 6.6 nA
   
Screening Logistics:  
Available: Yes
Storage Box: 171
Position in Box: 27
EP1 batch: 26
EP1 batch after irradiation: none
   
Shipment:  
Grid number: none
Position in grid: none
Arrival for irradiation: 16. Jul 2019
Sent for analysis after irradiation: 19. Jul 2019
Return for assembly: none
   
Irradiation:  
Date: 16. Jul 2019
Dose used: 37 Gy
Temperature: 20 °C
Position: none
Bias voltage: none     
   
Annealing:  
Date: 17. Jul 2019
Temperature: 80 °C
Duration: 48 h
   
Measurement results:  
Voltage for Gain 100: T = +20 °C: 377.8948922 V     T = -25 °C: 342.3806177 V
Voltage for Gain 150: T = +20 °C: 385.5626313 V     T = -25 °C: 349.6884335 V
Voltage for Gain 200: T = +20 °C: 389.8381267 V     T = -25 °C: 353.793433 V
Gain/Voltage slope at M = 100: T = +20 °C: 4.465308777 V-1     T = -25 °C: 4.886251491 V-1
Gain/Voltage slope at M = 150: T = +20 °C: 8.958263295 V-1     T = -25 °C: 9.255081489 V-1
Gain/Voltage slope at M = 200: T = +20 °C: 14.23480713 V-1     T = -25 °C: 14.85086081 V-1
Break-through voltage: T = +20 °C: 405.2600436 V     T = -25 °C: 369.1434959 V
   
Notes:


Version history

Time Author Change comment
03. May 2021 10:25:23 CEST oafedulidis Updated box and position via API.
05. Feb 2021 11:10:24 CET jreher Updated box and position via API.
11. Aug 2020 17:31:33 CEST jreher Updated APD characteristics via API.
27. Nov 2019 19:59:12 CET jreher Updated APD location via API.
25. Nov 2019 17:24:24 CET jreher Updated box and position via API.
30. Jul 2019 15:17:43 CEST spankonin Updated APD batch assignment via API.
23. Jul 2019 09:48:20 CEST markus.moritz
05. Jul 2019 13:58:53 CEST jreher Updated APD location via API.
24. Jun 2019 14:50:25 CEST jgrochowski Updated APD batch assignment via API.
03. Jan 2019 00:12:17 CET Tobias Corrected dark current unit.
12. Jan 2018 13:12:04 CET Tobias Imported from Hamamatsu datasheet.