Subdetector specification:  
Serial: 2420027522
Type: Hamamatsu Avalanche Photo Diode
Detector: unassigned
Unit: unassigned
Preamp: 0
Current location: Bochum
   
Installation information:  
Label: none
   
Manufacturer information:  
Wafer position: C03
Break-through voltage: 408 V
Voltage for Gain 100 (T=+25°C): 379.1 V
Dark current: 4.7 nA
   
Screening Logistics:  
Available: Yes
Storage Box: 27
Position in Box: 10
EP1 batch: none
EP1 batch after irradiation: none
   
Shipment:  
Grid number: none
Position in grid: none
Arrival for irradiation: 16. Jan 2019
Sent for analysis after irradiation: 28. Jan 2019
Return for assembly: none
   
Irradiation:  
Date: 21. Jan 2019
Dose used: 37 Gy
Temperature: 20 °C
Position: none
Bias voltage: none     
   
Annealing:  
Date: 22. Jan 2019
Temperature: 80 °C
Duration: 48 h
   
Measurement results:  
Voltage for Gain 100: T = +20 °C: 379.02785 V     T = -25 °C: 343.8302159 V
Voltage for Gain 150: T = +20 °C: 386.8424464 V     T = -25 °C: 351.1928959 V
Voltage for Gain 200: T = +20 °C: 391.2118027 V     T = -25 °C: 355.3319517 V
Gain/Voltage slope at M = 100: T = +20 °C: 4.730893027 V-1     T = -25 °C: 5.041967813 V-1
Gain/Voltage slope at M = 150: T = +20 °C: 8.979828458 V-1     T = -25 °C: 9.985896021 V-1
Gain/Voltage slope at M = 200: T = +20 °C: 14.37941388 V-1     T = -25 °C: 16.5046577 V-1
Break-through voltage: T = +20 °C: 406.9115743 V     T = -25 °C: 370.4923871 V
   
Notes:


Version history

Time Author Change comment
05. May 2021 14:07:22 CEST oafedulidis Updated box and position via API.
05. Feb 2021 10:51:18 CET jreher Updated box and position via API.
03. Feb 2021 18:17:24 CET jreher Updated box and position via API.
11. Aug 2020 17:24:05 CEST jreher Updated APD characteristics via API.
27. Nov 2019 19:34:16 CET jreher Updated APD location via API.
25. Nov 2019 17:13:00 CET jreher Updated box and position via API.
04. Jul 2019 11:09:52 CEST jreher Updated APD location via API.
12. Jun 2019 16:47:25 CEST jreher Updated APD batch assignment via API.
12. Jun 2019 16:32:20 CEST jreher Updated APD batch assignment via API.
28. Jan 2019 11:49:38 CET markus.moritz
03. Jan 2019 00:11:56 CET Tobias Corrected dark current unit.
12. Jan 2018 13:11:54 CET Tobias Imported from Hamamatsu datasheet.