Subdetector specification:  
Serial: 2418027317
Type: Hamamatsu Avalanche Photo Diode
Detector: unassigned
Unit: unassigned
Preamp: 0
Current location: Bochum
   
Installation information:  
Label: none
   
Manufacturer information:  
Wafer position: D10
Break-through voltage: 407 V
Voltage for Gain 100 (T=+25°C): 379 V
Dark current: 4.1 nA
   
Screening Logistics:  
Available: Yes
Storage Box: 24
Position in Box: 2
EP1 batch: none
EP1 batch after irradiation: none
   
Shipment:  
Grid number: none
Position in grid: none
Arrival for irradiation: 16. Jan 2019
Sent for analysis after irradiation: 25. Jan 2019
Return for assembly: none
   
Irradiation:  
Date: 21. Jan 2019
Dose used: 37 Gy
Temperature: 20 °C
Position: none
Bias voltage: none     
   
Annealing:  
Date: 22. Jan 2019
Temperature: 80 °C
Duration: 48 h
   
Measurement results:  
Voltage for Gain 100: T = +20 °C: 379.1123142 V     T = -25 °C: 343.8191394 V
Voltage for Gain 150: T = +20 °C: 386.92145 V     T = -25 °C: 351.1794305 V
Voltage for Gain 200: T = +20 °C: 391.2727391 V     T = -25 °C: 355.3187052 V
Gain/Voltage slope at M = 100: T = +20 °C: 4.472796587 V-1     T = -25 °C: 4.863415522 V-1
Gain/Voltage slope at M = 150: T = +20 °C: 8.52279338 V-1     T = -25 °C: 9.677090281 V-1
Gain/Voltage slope at M = 200: T = +20 °C: 14.33448925 V-1     T = -25 °C: 14.93463173 V-1
Break-through voltage: T = +20 °C: 406.7464141 V     T = -25 °C: 370.5798159 V
   
Notes:


Version history

Time Author Change comment
05. Feb 2021 10:50:52 CET jreher Updated box and position via API.
03. Feb 2021 18:17:00 CET jreher Updated box and position via API.
11. Aug 2020 17:23:33 CEST jreher Updated APD characteristics via API.
27. Nov 2019 19:33:41 CET jreher Updated APD location via API.
25. Nov 2019 17:12:44 CET jreher Updated box and position via API.
04. Jul 2019 11:09:27 CEST jreher Updated APD location via API.
12. Jun 2019 16:47:10 CEST jreher Updated APD batch assignment via API.
12. Jun 2019 16:32:05 CEST jreher Updated APD batch assignment via API.
12. Jun 2019 15:12:14 CEST jreher Updated APD batch assignment via API.
25. Jan 2019 14:18:58 CET markus.moritz
03. Jan 2019 00:11:50 CET Tobias Corrected dark current unit.
12. Jan 2018 13:11:51 CET Tobias Imported from Hamamatsu datasheet.